7-Week expedited program.
Shop remained open with minimal disruption.
CHALLENGE
The existing site was an operational BP petrol filling station with a single-story flat roof building and three fuel dispensers. Since it was a busy service station, there was limited space for redevelopment work, and the shop and forecourt had to remain open.
SOLUTION
Wyeth designed and managed this extension project. The team delivered a side extension to accommodate additional retail, Greggs areas, new Greggs Food To Go insert, an internal remodel and external fascia signage and decorations. A new foul water drainage solution was designed. Due to cold and wet weather conditions, the roof covering was changed from fiberglass to single-ply membrane.